incinerators from china

An operating test ought to be conducted to make certain that each of the control components have been properly installed and

that all areas of the incinerator, such as controls and safety devices, are in satisfactory operating condition. The

demands for prepurge and time between restarts should be confirmed. The evaluation should include but not limited to the

following;

?     Capacity tests of incinerator

?     Flame safeguard. The operation of the flame safeguard system ought to be verified by causing flame and  ignition

failures.  Operation of  the audible alarm (where applicable) and observable indicator ought to be verified. The shutdown

times should be verified.

?     Testing of shutdowns to the system.

?     Interlocks.

?     Combustion controls. The combustion controls should be stable and operate smoothly.

?     Programming       controls.       Programming       controls should   be   verified  as

 

controlling and cycling the unit in the intended manner. Appropriate prepurge, ignition, postpurge, and modulation ought to be

verified. A stopwatch ought to be used for verifying periods of time.

?    

?     A low voltage test ought to be run on the incinerator unit to satisfactorily demonstrate

the fuel supply to the burners will be automatically shut off before an incinerator malfunction results in the

reduced voltage.

?     Switches. All switches should be tested to verify proper operation. Emission tests. The exhaust of the

incinerator shall be tested to comply with local emission limits given in annex 1. Note that this test needs to be

seen by an independent body suitable by the CEB.

incinerator shall be tested to comply with local emission limits given in annex 1. Note that this test has to be

witnessed by an independent body acceptable by the CEB. The test shall include measurement of parameters given in annex